Projects


Gebze Darıca Metro Project

It is an 11-station metro project consisting of two lines of 15.40 km, starting from Darıca Sahil and reaching Gebze Organized Industrial Zone.
It has been designed with the aim of improving the transportation network by creating an alternative choice to the highway connection between Gebze Organized Industrial Zone and Gebze-Darıca districts and rail system integration to Gebze Marmaray Station.
Approximately 4km of the project was constructed as TBM tunnels, 2 Lovsuns TBM machines were used in tunnel excavations and ENZAN system was preferred as survey navigation system.
Within the scope of the project, the project contractor company EZE İNŞAAT A.Ş. and TSS Harita İnşş. And Eng. Tic. LTD. and the mapping activities were subcontracted to TSS Harita. The signed contract for the relevant project can be presented in the annex.

GDM Metro Project TBM Tunnels Measurement Procedures

As TSSTUNNELLING, we undertook the calibration, installation and TBM surveying system operation of the project, starting with the triangulation -GPS point facilities on the project route and the works carried out for the main TBM tunnels are as follows.
• Placement and measurements of the triangulation-GPS network
• Piles placement around the entrance concourse and station crossings
• Surface observations between triangulation points
• Production preparations of TBM entrance station structure (cradle concrete, shield leveling, steel cradle, push frame, start ring placement and all surveying activities before TBM installation and excavation)
• In-tunnel observation measurements and active progress of the navigation system
• Route line controls at station crossings

TBM Station Crossings Surveying Works

In the project, which has 11 stations in total, 4 stations were used as TBM transition and exit stations, and there is 1 switch structure within 4 stations.
The main works carried out in the station fabrication works are as follows.
• Station/Shaft area basis for production piles placement and measurements
• Integration of the piles used for station construction into the TBM route
• Bored pile applications, cap beam applications, girder beam applications, excavation cubage calculations, determination and application of displacement lines.
• Wall concrete application and mold controls
• Station structure shoring application and controls
• Arch mold application and controls
• All surveying works within the scope of the station.

TBM Route In-Tunnel And Surface Deformation

All structures and surfaces in and around the perimeter and concors of the 4 stations and switch structures on the TBM excavation route were monitored using several deformation techniques and presented as data to the Geotechnical unit and thus TBM excavations were actively monitored daily. The techniques and methods used in deformation measurements are as follows.
• Ground settlement bolt tracking (Geometric leveling)
• Building settlement bolt tracking (Geometric leveling)
• Building bending bolt tracking (by making 3d measurements with the help of Totalstation)
• Inclinometer measurements (movements in the excavation cover with the help of an inclinometer)
• Piezometer measurements (excavation cover water level with the help of a piezometer)

Supply and Construction of Halkali-Ispartakule Railway Line Construction and Electromechanical Systems Within The Scope of Halkali-Kapikule New Railway Construction

It plans to build a new high-speed railway line from Halkali to Ispartakule and Ispartakule to Çerkezköy (the Project) in two different tenders and sections. The Project will be located in the Istanbul region and Tekirdağ province.
The first part of the Project covers Halkalı - Ispartakule section and includes 7km TBM tunnel excavation, the tunnel will be excavated with 2 CREG brand TBMs that will enter from Halkalı entrance structure and the surveying system to be used on the TBM is PPS navigation system.

As TSS Harita İnş LTD ŞTİ, we undertake distributorship of PPS/TACS navigation systems in Turkey, Middle East and Turkic Republics, the project management has deemed it appropriate that all surveying activities based on TBM be carried out by our company and for this reason, GÜLERMAK-YAPIYAPI-TAŞYAPI RAILWAY CONSTRUCTION PARTNERSHIP VENTURE and TSS Harita İnş. ve Müh. Tic LTD ŞTİ Companies signed a subcontractor agreement between the subcontractor contract and mapping activities were transferred to TSS Harita company. The signed contract for the relevant project can be presented in the annex.

Surveying Activities Performed and Ongoing Surveying Activities within the Scope of Halkalı-Ispartakule Railway Line within the Scope of Halkalı Ispartakule New Railway Construction

As TSSTUNNELLING, we undertook the calibration, installation and TBM surveying system operation in the project, starting with the triangulation -GPS point establishments on the project route,
The works carried out for TBM tunnels are as follows.
• Survey and measurements of the triangulation-GPS network
• Piles placement around the entrance concourse and station crossings
• Surface observations between triangulation points
• Production preparations of TBM entrance station structure (cradle concrete, shield leveling, steel cradle, push frame, start ring placement and all surveying activities before TBM installation and excavation)
• In-tunnel observation measurements and active progress of the navigation system
• Conveyor belt manufacturing and heel concrete and in-tunnel belt layout measurements
• TBM excavation mirror support process surveying activities
• Cross Passage NATM production measurements
• TBM tunnel axis horizontal vertical element calculations

TBM Station Exit Structure

Halkalı Ispartakule New Railway Construction includes 2 stations and 1 shaft consisting of entrance and exit structure, TBM entrance mirror is from Halkalı open field structure and exit structure consists of a concourse structure in Ispartakule section. There are 13 CPs within the 7 km tunnel.
The main works carried out in station fabrication, shaft and CP works are as follows.
• Station/Shaft area manufacturing pile installation and measurements
• Integration of the piles used for station construction into the TBM route
• Bored pile applications, cap beam applications, girder beam applications, excavation cubage calculations, determination and application of displacement lines.
• Wall concrete application and mold controls
• Station structure shoring application and controls
• Arch mold application and controls
• All surveying works within the scope of the station.

TBM Route In-Tunnel and Surface Deformation

The deformation measurements made in military zones, roads, building clusters and ponds on the TBM excavation route are submitted as data to the Geotechnical unit and TBM excavations are actively monitored daily. The techniques and methods used in deformation measurements are as follows.
• Ground settlement bolt tracking (Geometric leveling)
• Building settlement bolt tracking (Geometric leveling)
• Building bending bolt tracking (by making 3d measurements with Totalstation)
• Inclinometer measurements (movements in the excavation cover with an inclinometer)
• Piezometer measurements (excavation cover water level with a piezometer)

Bahçe-Nurdağ Railway Project (Gaziantep)

• Healthy and precise operation of the navigation system during tunnel progress,
• Calculation and evaluation of observations.
• Updating the project located in the earthquake zone according to the post-earthquake ground motions.
• Measurement, drawing and evaluation of tunnel sections
• Collimation checks and renewals for instrument measurement accuracy
• Project revision after identified deviations
• Excavation of art structures, cubage calculations and applications

European Side Drinking Water Tunnels Project (Istanbul)

• Healthy and precise operation of navigation systems during tunnel progression
• Calculation and evaluation of survey measurements.
• Measurement, drawing and evaluation of in-tunnel cross sections
• Collimation checks and renewals for instrument measurement accuracy

Mahmutbey-Bahçeşehir-Esenyurt Metro Project (Istanbul)

• Healthy and precise operation of navigation systems during tunnel progression
• Calculation and evaluation of survey measurements.
• Measurement, drawing and evaluation of in-tunnel cross sections
• Collimation checks and renewals for instrument measurement accuracy

Europe 2nd Region 1st Section Tunnel Construction (Istanbul)

• Healthy and precise operation of navigation systems during tunnel progression
• Calculation and evaluation of survey measurements.

Buca - Üçyol Metro Project (Izmir)

• Establishment of triangulation network before tunnel excavations
• Identification of areas where deformation may occur and determination of measurement frequency
• Healthy and precise operation of navigation systems during tunnel progression
• Calculation and evaluation of survey measurements.
• Measurement, drawing and evaluation of in-tunnel cross sections
• Collimation checks and renewals for instrument measurement accuracy

Ayvalıdare Wastewater Tunnel (Istanbul)

Tacs system installation and commissioning, creation of new routes and intermediate installations.
Personnel trainings.

European Side Drinking Water Tunnels Project (Istanbul)

Installation and commissioning of Enzan navigation system in 2 TBMs.
Personnel trainings.
Service for malfunctions occurring during progress.

Çorlu Ergene Basin Project (Tekirdağ)

Enzan system installation and commissioning.
Personnel trainings.

Yoncalı Dam Transmission Tunnel Project (Malatya)

DDJ system installation and commissioning.
Personnel trainings.

Silvan Dam Transmission Tunnel Section 1 (Diyarbakır)

Tacs navigation system installation and commissioning.
Personnel trainings

Koçali Irrigation Approach Tunnel Project (Adıyaman)

VMT Gyro navigation system installation and commissioning.
Personnel trainings.

Halkalı-Istanbul Airport Metro Project (Istanbul)

Enzan navigation system installation and commissioning in 4 TBMs.
Personnel trainings.

Gayrettepe-Istanbul Airport Metro Project (Istanbul)

Tacs in 3 TBMs, VMT navigation system installations and commissioning in 2 TBMs.
Personnel trainings.

Gebze Darıca Metro Project (Kocaeli)

Enzan navigation system installation and commissioning in 2 TBMs.
Personnel trainings.

Kaynarca-Pendik-Tuzla Metro Project (Istanbul)

Tacs navigation system installation and commissioning in 2 TBMs.
Personnel trainings.

Karamürsel Drinking Water Tunnel Project (Kocaeli)

Enzan system installation and commissioning.
Personnel trainings.

Mahmutbey-Bahçeşehir-Esenyurt Metro Project (Istanbul)

Installation and commissioning of Enzan navigation system on 2 TBMs.
Personnel trainings.
Service for malfunctions that occurred during progress.

Europe 2nd Region 1st Section Tunnel Construction (Istanbul)

VMT system installation and commissioning.
Personnel trainings.

Buca - Ucyol Metro Project (Izmir)

Enzan in 2 TBMs, DDJ navigation system installations and commissioning in 2 TBMs.
Personnel trainings.

Bahçe-Nurdağ Railway Project (Gaziantep)

Enzan system installation and commissioning.
Personnel trainings.
Service for malfunctions during progress.

Çöllolar Coal Mine (Kahramanmaraş)

Establishment of automatic geodetic and geotechnical monitoring network for monitoring soil movements, determination and installation of instruments.
Personnel trainings.

Wakrah & Wukair Wastewater Tunnel Project (Doha/Qatar)

Installation and commissioning of PPS navigation system on 2 TBMs.
Personnel trainings.

Sao Paulo Metro Line 6 Project (Sao Paulo/Brazil)

Installation and commissioning of PPS navigation system on 2 TBMs.
Personnel trainings.
Consultancy to personnel at the beginning of TBM excavations.

Algiers Metro Project (Algeria):

PPS navigation system installation and commissioning.
Personnel trainings.

Project Relevant Administration Yüklenici
Bolu Tekke Dam Reservoir Base Map Production State Hydraulic Works 5th Regional Directorate Akgenç İnşaat Elektrik Nak.Tur. San ve Tic. LTD. ŞTİ.
Bademli Pond Vana Access Road Project State Hydraulic Works 18th Regional Directorate Hydrotec Mühendislik İnş. LTD. ŞTİ.
Alpagut Pond Ready Map and Orthophoto Production State Hydraulic Works 3th Regional Directorate Hydrotec Mühendislik İnş. LTD. ŞTİ.
Tımarlı Irrigation 2nd Part Construction Base Map and Orthophore Production State Hydraulic Works 5th Regional Directorate NRT Enerji Madencilik İnşaatA.Ş.
Inegazili Pond Irrigation Current Map and Orthophoto Production State Hydraulic Works 5th Regional Directorate Hydrotec Mühendislik İnş.LTD. ŞTİ.
Karaman Güldere Irrigation Ready Map Production and Work End Measurements State Hydraulic Works 4th Regional Directorate Düntaş İnşaat A.Ş.
Niğde Asmasız Pond Baseline Map Production and End of Work Measurements State Hydraulic Works 4th Regional Directorate Düntaş İnşaat A.Ş.
Carrying out Mapping Works of Söğüt Savcıbey Pond State Hydraulic Works 3th Regional Directorate Yılka İnşaat LTD. ŞTİ.
Kırıkkale Mahmutlar Şarklısı Pond Mapping Works execution State Hydraulic Works 5th Regional Directorate Mehmet Koray DEĞER
Kırıkkale Balışeyh – Akçakavak Ponds Irrigation Carrying out Mapping Works State Hydraulic Works 5th Regional Directorate Yılka İnşaat LTD. ŞTİ.
Konya Ilgın Belekler Pond Mapping Services State Hydraulic Works 4th Regional Directorate Yılka İnşaat LTD. ŞTİ.
Konya Seydişehir Kuran Flood Protection Facilities Cartography Services State Hydraulic Works 4th Regional Directorate Yılka İnşaat LTD. ŞTİ.
Tashkent Chetmi Town Flood Protection Facilities Cartography Services State Hydraulic Works 4th Regional Directorate Köseoğlu Yol Yapı A.Ş.
Konya 8th Section EC and TİGH Project Construction State Hydraulic Works 4th Regional Directorate Asil İnşaat A.Ş.
Konya 14th Section EC and TİGH Project Construction State Hydraulic Works 4th Regional Directorate Ali Demirok A.Ş.
Konya Meram Gökyurt Pond and Irrigation Work Cartography Services State Hydraulic Works 4th Regional Directorate Eresu İnşaat LTD.ŞTİ.
Eskişehir Mihalgazi Alpagut Pond Expropriation Works State Hydraulic Works 4th Regional Directorate Abad Proje – Gürcan Proje İş Ortaklığı
Erzurum Horasan Road TCDD Current Production TCDD 4th Regional Directorate SOM Proje
Sivas Divriği TCDD Base Map Production TCDD 4th Regional Directorate SOM Proje
Construction and Rehabilitation of Art Structures in the Streams of Düzce Province Cartography Services State Hydraulic Works 5th Regional Directorate Yılka İnşaat LTD. ŞTİ.
Bolu Gerede District Dayıoğlu and Çeltek Streams Cartography Services State Hydraulic Works 5th Regional Directorate NRT Enerji Madencilik İnşaat A.Ş.
Tımarlı Irrigation 2nd Section Construction Work AT Site Delivery Services State Hydraulic Works 5rd Regional Directorate NRT Enerji Madencilik İnşaat A.Ş.
Bartın Kozcağız Yeni Hamidiye Settlement and Lands Work Cartography Services State Hydraulic Works 23rd Regional Directorate Köseoğlu–Gülsu İş Ortaklığı
Kastamonu Ekincik Pond Project Construction Work Base Map Production Work State Hydraulic Works 23rd Regional Directorate NETSU Grup Mühendislik
Kastamonu Acısu Pond Project Construction Work Base Map Production Business State Hydraulic Works 23rd Regional Directorate NETSU Grup Mühendislik
Pavement Arrangement Work in Central Neighborhoods Cartography Services Konya Metropolitan Municipality NSTONE LTD.ŞTİ.
Parquet Border Construction Work in Cemeteries of 31 Districts Konya Metropolitan Municipality Kaya Yapı
33 Neighborhood Asphalt Paving Work Mapping Services Konya Metropolitan Municipality Kocaerlerr Harfiyat Nakliyat İnşaat LTD. ŞTİ.
Trench Repair and Construction Work Surveying Services Konya Meram Municipality KM Grup LTD.ŞTİ.
Central Mosque Environmental Planning Work Cartography Services Konya Karatay Municipality Köseoğlu Yol Yapı A.Ş.
Çankırı Circassian Wind Energy Systems current construction work Ministry of Energy Natural Resources Gül Mühendislik
Bartın province flood protection facilities improvement work State Hydraulic Works 233rd Branch Directorate Özbek İnşaat LTD. ŞTİ.
Mine site manufacturing maps YTK Baştaş Çimento
Mine site manufacturing maps YTK Tamtaş Çimento
Mine site manufacturing maps State Hydraulic Works 1st Region Directorate Hidrokar İnşaat A.Ş.
Mine site manufacturing maps YTK Konya Çimento
Mine site manufacturing maps State Hydraulic Works 23rd Regional Directorate Hidrokar İnşaat A.Ş.
Mine site stock measurements Baştaş Cement Baştaş Çimento
Mine site stock measurements Tamtaş Cement Tamtaş Çimento
Mine site stock measurements Konya Cement Konya Çimento
Burdur Ağlasun road current map production Highways General Directorate 13th Region Düzlem Harita
Kahramanmaraş Elbistan thermal power plant diversion channel base map construction work TEİAŞ 12th Regional Directorate Düzlem Harita
Kahramanmaraş earthquake residences base map and plan construction work AFAD GENERAL DIRECTORATE Abad Proje İnşaat
Bartın River and its tributaries improvement work base map making State Hydraulic Works 23rd Regional Directorate 58 Yapı & Hidrokar İnşaat İş Ortaklığı
Niğde Asmalı Pond Irrigation Expropriation Works State Hydraulic Works 4rd Regional Directorate Düntaş İnşaat A.Ş.
Cihanbeyli Flood Protection Facilities Expropriation Works State Hydraulic Works 4rd Regional Directorate Düntaş İnşaat A.Ş.
Eskişehir Atalan Pond Expropriation Works State Hydraulic Works 3rd Regional Directorate Abad Proje – Gürcan Proje İş Ortaklığı
Antalya-Batman-Burdur-Osmaniye-Aksaray provinces Solar Energy Systems base map construction work Ministry of Energy Natural Resources Düzlem Harita
Çankırı Circassian Wind Energy Systems current construction work Ministry of Energy Natural Resources Gül Mühendislik
Konya Taşkent Blue Tunnel Construction Currently Ready mapping and surveying work State Hydraulic Works 4th Regional Directorate Abad Proje & İmaj Mühendislik iş ortaklığı
Cobblestone map service in various neighborhoods of Konya Karatay Konya Karatay Municipality Alpyol İnşaat

Bartın River and its tributaries reclamation survey work;

-Aerial photographs were taken with a DJI Matrice 300 RTK drone in approximately 6300 ha area for the production of the survey map in Bartın province.
-Since the land is a region with dense trees and height differences, reference points were taken from the land with our field team on site for local measurement.
-Our 3D stereo drawing team balanced and evaluated the aerial photographs with the help of the reference and control points we took in the field and started drawing.
-Again, our field team completed static sessions in the field. Leveling calculations were made.
-For the underwater measurements requested for the Bartın River, bathymetric measurements were completed at the Bartın River and Black Sea connection with the help of a boat and supported by terrestrial and photogrammetric methods.
-All controls related to land measurements were carried out with the drawing completed after the measurements were completed.
-Expropriation files were prepared.
-Account volumes and survey volumes were approved and delivered.

Eskişehir Mihalgazi Alpagut Pond construction work;

-Piles were constructed for the static session.
-With the help of the established points, our ground measurement team, which was ready on site, made purchases for ground control points and reference points.
-In the survey map production work carried out in Eskişehir province, aerial photographs were first created with DJI Phantom 4 RTK drone.
-After the land measurements were completed, our 3D stereo drawing team completed the drawing by evaluating and balancing the land photographs.
-After the digital submission of the created state-of-the-art map, land controls were completed.
-Expropriation files were prepared
-Account volumes and survey volumes were approved and delivered.

Bastas Cement mine site stock measurements

-Static session was made and polygons were established.
-The establishment of ground control points was completed with the help of the established polygons
-Aerial photographs were produced with DJI Mavic 3 RTK drone for monthly stock measurements at actively producing mine sites.
-3D Stereo drawing team completed balancing, valuation and drawing processes
-Annual production maps requested at mining sites were prepared.

Konya Meram District Base map production;

-In Meram district of Konya province, aerial photographs were first taken with DJI Mavic 3 brand drone for the production of a state-of-the-art map.
-Control and reference points were taken by our field team.
-After the land measurements were completed, our 3D stereo drawing team completed the drawing by evaluating and balancing the land photographs.

Diyarbakır Silvan Babakaya Tunnel completion work;

-Our field teams constructed 12 piles for the Tunnel Supply Work in Diyarbakır province.
-After the completion of pilye measurements and calculations, ground control points were established in the field.
-Aerial photographs were taken with DJI Matrice 300 RTK drone.
-Balancing, valuation and drawing processes were completed by our 3D Stereo drawing team.
-Field controls were completed after the digital delivery of the produced state-of-the-art map.

AFSAR BAĞBASI HADIM Tunnel Construction Work

The purpose and scope of the project is to transfer the waters collected in Afşar Dam and the waters diverted from Taşkent, Hadim, Kongul and Kurudere Regulators to Bağbaşı dam reservoir via Afşar-Bağbaşı Diversion Canal + Tunnel and from there to Konya-Çumra plain via Mavi Tunnel.

The project is located in Hadim district of Konya province, 12km of the approximately 18km water tunnel will be excavated with Herrenknecht TBM and the measurement system to be used on the TBM is VMT-TUNIS navigation system.
After the request of İmaj / Abad Partnership, which is the project contractor partnership, due to the disruptions and operational problems experienced in the VMT-TUNİS operating system in the project, which has been under construction and excavation for many years, İMAJ ALTYAPI-ABAD PROJECT PARTNERSHIP and TSS Harita İnş. ve Müh. Tic. LTD ŞTİ, a navigation system tracking contract was signed and surveying activities were transferred to TSS Harita. The signed contract for the relevant project can be presented in the annex.
Surveying Activities Performed and Ongoing Surveying Activities within the Scope of Afşar Bağbaşı Hadimi Tunnel Supply Work.
• Base piling installation and surveying of the water intake structure and shaft areas
• In-tunnel observation measurements
• Active operation and reporting of VMT-TUNIS navigation system
• TBM Route revisions are made and submitted to DSİ Regional Administration